Review Simulator Page Flow

    XMLWordPrintable

    Details

    • Type: Story
    • Status: Open
    • Priority: Minor
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: TVB-Simulator
    • Labels:
      None
    • Epic Link:
    • Sprint:
      VBC Sprint 9
    • TVB-C Task:
      8.2 Pipeline Integration

      Description

      This is intended as an umbrella story, describing the currently not working parts of the Simulator page.

      To be decided (based on  estimated fix duration) if these deserve their own task/subtask, or can be group some other way when planning/fixing. 

      1. Bold monitor launching fails when sample_period is smaller than simulation_length and doesn't give any suggestive message, it just fails TVB-2642
      2. When a PSE Launch with Bold monitor can be launched successfully (if not failed as above), but the Discrete Visualizer won't work for it, it doesn't give any error in Pycharm but you just won't see anything when you click on it)
      3. Deleting simulation from history is not finalized TVB-2724
      4.  Simulation with Spatial Average Monitor can be launched but it will show up with red at Operations and the error only says: "'NoneType' object has no attribute 'size'". TVB-2701
      5. Not bug, but would be nice to display a message in the Simulator page in case there is no Connectivity in the project.

       

      EDIT: I changed the title, as what is left are mostly improvement suggestions, not missing functionality or major bugs, except for the PSE on BOLD.

      Robert Francisc Vincze Could you pls retry the BOLD PSE and create a bug with a proper stack-trace, if it still reproduces?

        Gliffy Diagrams

          Attachments

            Issue Links

              Activity

                People

                Assignee:
                Unassigned Unassigned
                Reporter:
                robert.vincze Robert Francisc Vincze
                Votes:
                0 Vote for this issue
                Watchers:
                2 Start watching this issue

                  Dates

                  Created:
                  Updated:

                    Time Tracking

                    Estimated:
                    Original Estimate - 2 weeks, 4 days
                    2w 4d
                    Remaining:
                    Time Spent - 4 hours, 30 minutes Remaining Estimate - 2 weeks, 3 days, 3 hours, 30 minutes
                    2w 3d 3h 30m
                    Logged:
                    Time Spent - 4 hours, 30 minutes Remaining Estimate - 2 weeks, 3 days, 3 hours, 30 minutes
                    4h 30m